All Projects  /  Project 06
Energy · CSR project

Solar Power Installation — Energy for LearningClean, uninterrupted electricity for the entire school.

CSR Funding Ask
₹ 15,00,000
750 students & 50 staff · 60 days · Oxford Public School, Waigaon, Wardha
Solar Power Installation
₹ 15,00,000
Project Cost
750 students & 50 staff
Beneficiaries
60 days
Timeline
Executive Summary

Solar Power Installation

Oxford Public School relies entirely on Maharashtra State Electricity Board power, which is subject to frequent outages — disrupting learning, especially during examination periods. With India's national call for institutional energy conservation, a solar solution is both a practical and patriotic priority.

This project installs a 10–13 kW rooftop solar power system with battery backup, providing clean, uninterrupted electricity to the entire school.

The Problem

Load-shedding during examination periods directly disrupts learning, and the school's monthly electricity costs divert funds that could otherwise go to academics. A reliable, independent power source removes this recurring constraint permanently.

The Proposal

Installation of a 10–13 kW rooftop solar system with hybrid inverter and battery backup, powering all four floors:

Budget Breakdown

Transparent, itemised costing.

Line ItemUnit Cost / BasisQtyAmount
Solar panels10–13 kW system1₹ 4,50,000
Hybrid inverterLump sum1₹ 1,00,000
Lithium battery bankLump sum1₹ 7,00,000
Mounting, wiring & commissioningLump sum1₹ 2,50,000
TOTAL₹ 15,00,000

Expected Impact

Implementation Timeline

  1. Week 1–2Site survey, vendor finalisation, panel procurement
  2. Week 3–6Mounting, wiring, battery installation
  3. Week 7–8Commissioning, testing, handover
Regulatory Compliance & Tax Benefit

This project is eligible CSR expenditure under the Companies Act 2013, Section 135, Schedule VII(ii) — Promotion of Education — and aligns with NEP 2020 and UN SDG 4 (Quality Education). Contributions qualify for 80G tax deduction; Form 10BE is issued for every donation. Chetana Education Society is independently audited and provides quarterly progress reports with photographs and fund-utilisation statements.

← Sports InfrastructureMulti-Floor Sanitation →
About the Implementing Organisation

A 53-year legacy of service.

Chetana Education Society was founded in 1973 in Wardha, Maharashtra. Since launching its teacher-training college in 1991, the Society has educated 35,000+ first-generation learners and today runs 2 schools and 12 colleges serving 2,250+ students annually. It is a CSR-1 registered Implementing Agency (Reg. CSR00095049) with valid 12A and 80G certification (2025–2028).

Oxford Public School, Waigaon is the Society's flagship K–12 institution: 750 students, Nursery to Class XII, drawn from 30+ farming villages in Wardha district where 95% of families earn ₹10,000–12,000/month. The school has produced NTS scholars, Navodaya Vidyalaya selections, World-PEC champions, national cricket runners-up, and an international Lathi-Kathi representative — proof of what these children can achieve when given the right environment.

Get in Touch

Ready to discuss any of these projects with your CSR team.

All CSR engagement, funding agreements and statutory correspondence are handled directly by Chetana Education Society as the registered Implementing Agency. Please reach us below.

Implementing Agency · CSR-1 registered

Chetana Education Society

Dr. Chetana Sawai · Secretary · Physiotherapist, MSW, PhD
Address
Shrawasti Nagar, Sawangi Meghe Road,
Wardha, Maharashtra 442001, India
Registrations
CSR-1 Reg. No. CSR00095049 · 12A & 80G certified (2025–2028)
Transparency. Chetana provides quarterly progress reports with photographs and fund-utilisation statements, and issues Form 10BE for every donation. On confirmation we execute an MoU / Letter of Intent and share fund-transfer details. A school site visit is welcome at any time.
✉ Email Chetana ← Back to all projects